Replacement of all cables (power, signals, data) and reconnection to the existing equipment from the electrical rooms.
Wiring of the new equipment installed on the new sections.
Installation of lighting and service sockets on the new sections.
Migration to a fail-safe PLC, integrating safety and process management within a single controller.
Recommissioning of the renovated production line.

Some figures

  • Over 600 metres of cable trays installed on steel structures.
  • Over 4 kilometres of cables installed.
5 – eBolt
3 – eBolt
11 – eBolt
6 – eBolt
12 – eBolt

You may also be interestedin these articles

Rectangle – eBolt

PANEL

Discover our projects

Read More

Header – eBolt

ENERGY

Discover our projects

Read More

Thumb News 3D – eBolt

Maximising efficiency and profitability through 3D modelling

Optimising efficiency and profitability in industrial electrical engineering has reached a new level with the use of 3D modelling, in particular thanks to EPLAN Pro Panel.

Read More